           5243.201 General.

           5243.204 Administration.

                5243.204-70 Definitization of change orders.

                5243.204-70-1 Scope.

 

SUBPART 5243.2 CHANGE ORDERS

 

5243.201 General.

(S-90) (a) Each undefinitized change order  shall include a not-to-exceed price unless the CCO waives this requirement.

(b) The policies and procedures of DFARS 217.74  shall be applied to change orders (except value engineering change proposals (VECPs)) to  the maximum extent practicable.

(c) The use of VECPs are encouraged due to the  potential savings and system improvements that may be realized.

(1) Prompt action shall be taken to implement  those VECPs deemed to be technically sound.

(2) When considering VECPs, contracting officers  shall consider the impact on the projected savings that the normal negotiation and  definitization process would have versus use of an unpriced change order. Unpriced  contract modifications that implement VECPs shall:

(i) Define minimum unit cost savings, and

(ii) Define maximum development/implementation  costs

 

5243.204 Administration.

 

5243.204-70 Definitization of change  orders.

 

5243.204-70-1 Scope.

(b) Submit the required contracting officer  notice to DASN(AP) by email at RDAJ&As.fct@navy.mil with the subject [Activity  Name] Contracting Officer Notice pursuant to DFARS 243.204-70-1 FMS/SAP Unpriced  Change Orders.

5243.204-70-7 Plans and Reports.

See 5217.7405 for reporting requirements.

 